Completed in July 2026, this project involved replacing the Track 3 rail weigh scale inside the loadout building at Mosaic’s Belle Plaine potash facility.

Our team removed the existing scale in three sections, refurbished the support concrete piers, and installed a new 63-foot by 10-foot scale with a reinforced concrete deck and eight load cells. A gantry and roller system allowed crews to move the large scale sections through the building’s restricted clearances.

Working alongside Mosaic and the scale vendor, we supported installation and commissioning, including rail placement and platform reinstatement. The project was completed on time, under budget, with zero safety incidents.